Introduction of Surveying and Levelling
General:
The primary reference at water-level recording stations is a set of stable bench-marks, installed in locations where their level should not change. Upon initial set-up of a station, the levels of the relevant parts of the installation are established and recorded by means of accurate levelling. At least every two years, the levels of the staff gauges, sensor level, internal gauge, tower structure and benchmarks should be measured relative to each other as a check that records are not in error due to bank subsidence or other movement.
Accurate levelling is thus a particularly important part of site establishment, installation and quality assurance. All staff shall be thoroughly familiar with its theory and practice. Levelling and surveying methods are also used for measurements of river channel and lake configurations. Often, less accurate methods can be used for this work than for water-level recording stations, although the techniques are common.
Definitions:
Differential levelling is the term applied to any method of measuring directly with a graduated staff the difference in elevation between two or more points.
Differential levelling is the term applied to any method of measuring directly with a graduated staff the difference in elevation between two or more points.
Precise levelling is a particularly accurate method of differential levelling which uses highly accurate levels and with a more rigorous observing procedure than general engineering levelling. It aims to achieve high orders of accuracy such as 1 mm per 1 km traverse.
A level surface is a surface which is everywhere perpendicular to the direction of the force of gravity. An example is the surface of a completely still lake. For ordinary levelling, level surfaces at different elevations can be considered to be parallel.
A level datum is an arbitrary level surface to which elevations are referred. The most common surveying datum is mean sea-level (MSL), but as hydrological work is usually just concerned with levels in a local area, we often use:
An assumed datum, which is established by giving a benchmark an assumed value (e.g. 100.000 m) to which all levels in the local area will be reduced. It is not good practice to assume a level which is close to the actual MSL value, as it creates potential for confusion.
A reduced level is the vertical distance between a survey point and the adopted level datum.
A bench mark (BM) is the term given to a definite, permanent accessible point of known height above a datum to which the height of other points can be referred.
It is usually a stainless steel pin embedded in a substantial concrete block cast into the ground. At hydrological stations rock bolts driven into bedrock or concrete structures can be used, but structures should be used warily as they themselves are subject to settlement. The locations of benchmarks shall be marked with BM marker posts and/or paint, and recorded on the StationbHistory Form.
A set-up refers the position of a level or other instrument at the time in which a number of observations are made without mooring the instrument. The first observation is made to the known point and is termed a backsight; the last observation is to the final point or the next to be measured on the run, and all other points are intermediates.
A run is the levelling between two or more points measured in one direction only. The outward run is from known to unknown points and the return run is the check levelling in the opposite direction.
A close is the difference between the starting level of the initial point for the outward run and that determined at the end of the return run. If the levels have been reduced correctly this value should be the same as the difference between the sum of the rises and falls and also the difference between the sum of the backsights and foresights.
Height of Collimation is the elevation of the optical axis of the telescope at the time of the setup. The line of collimation is the imaginary line at the elevation.
Orders of levelling refer to the quality of the levelling, usually being defined by the expected maximum closing error.
Comments
Post a Comment